Quick answer

A turnover package index should define the package boundary and list every required handover record in a stable order. Group documents by system, asset or contractual section; identify each item by document number, title, revision, status and filename; then reconcile the completed index with the actual package before transfer.

A turnover package may contain thousands of files from engineering, procurement, construction, quality, commissioning and operations. The index connects those records to a defined scope and gives the recipient a way to confirm what was transferred.

Define the package boundary first

Decide whether the package is organised by system, subsystem, asset, area, contract, discipline or completion milestone. State what is included and excluded. When several packages overlap, name the authoritative home of each record and use cross-references rather than uncontrolled duplicates.

Agree the index structure

A practical package often contains sections for governing documents, design basis, approved drawings, vendor data, inspection and test records, material certificates, commissioning results, punch-list closeout, operations manuals, warranties and final acceptance records.

The exact sections depend on the asset and contract. Agree them early enough that teams can file records as they are produced.

Fields for each indexed item

Separate completeness from acceptance

A file may be present but not accepted. The index should distinguish received, reviewed, approved, final and not applicable states according to the agreed workflow. Avoid a single “complete” flag that hides whether the document passed technical review.

Index at the start, reconcile at the endBuilding the index at handover is too late to discover that a required certificate was never requested. Use it as a planning tool throughout delivery.

Run the final reconciliation

  1. Freeze the candidate package.
  2. Export the approved turnover index to a checkable spreadsheet.
  3. Compare every expected filename or document number with the package.
  4. Review unlisted files and duplicate candidates.
  5. Open critical files and confirm usability, approval and correct content.
  6. Resolve or formally accept every exception.
  7. Issue the package and index through the required handover process.

Make the transfer usable

Test navigation from the index to the files. Check links, folder paths, naming, native formats and any viewer requirements. The receiving operator should be able to find a required record without relying on the person who assembled the package.

When Deliverable Preflight helps

Deliverable Preflight verifies the file manifest side of turnover. It compares CSV or XLSX rows with a local folder and produces a full exception report. It does not approve quality records or determine whether a package satisfies the contract.

Check the manifest before transfer

Use a deterministic preflight to find missing, unexpected and ambiguous files while the project team can still correct them.

View Deliverable Preflight in Microsoft Store →

Related guides

Read preparing an as-built register and managing vendor document registers.

Further reading

Questions people ask

What is a turnover package index?

It is the controlled manifest of records delivered for a defined system, asset, contract or handover scope.

When should the turnover index be created?

Create and agree it early, then maintain it through the project. Final reconciliation happens before transfer.

Does file presence mean a turnover record is accepted?

No. Presence, technical acceptance and contractual completeness are separate states and should be recorded separately.